Main components arrive at Hvidebæk

Weiss A/S is as turnkey contractor currently installing a 7 MW straw fired plant in Jerslev Sj.(DK). It’s a replacement and upgrade of an existing plant that Weiss installed some 20 years ago. Installation is well in progress and commissioning is planned to start late August for final handover mid-November 2017.

Key sub-contractors are Arkikon Aps (architect & building advisor) and Østermark A/S (building contractor). Lifting of the main components took place in one day (Thursday in week 16) where 8 trucks were unloaded and components lifted into place by BMS-VST (cranage company).

A challenge is that the existing plant will be in operation during most of the installation period due to security of supply. Careful planning for safe and efficient site work has also been completed as building erection and plant installation will take place alongside.